W.J. Zahnow Elementary School

Owner Waterloo Community Unit School District No. 5
Design Build Mechanical icon Mechanical
Value of icon's Work $1,500,000

icon Mechanical was responsible for the value engineering, MEP coordination, redesign, installation and commissioning of all new HVAC systems in the facility. This included installing a Daikin System that consisted of 6 individual condensing units with a total of 54 fan coil units and 48 branch selector boxes stretched out across the school. Then we installed 1 roof top unit to condition the gymnasium/multi-purpose room.

icon Mechanical self-performed the installation with our own trade workers. There was over 5,500 foot of refrigerant pipe and over 1,500 linear feet of spiral and rectangular ductwork that went into the building. This entire project was completed in less than 2 ½ months. With the new Daikin System, the school has seen an incredible energy savings.